The mayors of Keratsini and Perama appealed to the Council of Ministers as residents of the area in 2021 – Which projects are excluded
They stop temporarily three main mandatory investment projects in the port of Piraeus, following a relevant decision of the suspensions committee of the Council of State discussed on March 24, 2023 following an appeal by mayors (Keratsiniou-Perama) and residents of the area in 2021.
It’s about her southern extension of the port of Piraeuswhich will allow the docking of large cruise ships (over 300 meters), giving impetus to the efforts to develop and strengthen the cruise, the dredging project in the central port of Piraeus, but also that of the expansion in the port of Heraklion.
According to the project study, the expansion of the Car Handling Station at the Heraklion Pier, in the commercial port of Keratsini, foresees the extension of the pier by 35 acres. Its new dimensions will be 1,100 m long platforms with an operational depth of 12.50 m and a total area of ​​110,000 m2. Also, the project includes the improvement and upgrading of the existing port and E/M facilities.
This investment is expected to strengthen the competitiveness of the Port Car Station, as it will create 5,400 new car spaces.
Decision 47/2023 of the Council of State essentially states that in order for the AEPO (Decision to Issue Environmental Conditions) to be issued in order for the specific projects to proceed, it must be accompanied by and take into account the traffic study of the port which investigates the traffic loads of the area, extracting specific data whether or not the port burdens the city and submitting relevant proposals.
In the decision it is pointed out that in view of the relationship of communication and complementarity of the stages of the environmental licensing of plans and projects as well as the provisions of the new regulatory plan of Attica for the functional interconnection of port activities with the urban fabric through integrated traffic planning, as well as for the training of a specialist of a plan with directions for traffic organization for the requirements of the tourism that will come from the cruise is feasible and at the same time it is necessary to prepare a comprehensive traffic study during the stage of the environmental licensing of the projects either during the revision of the already approved ones or during the approval of new ones.
Regarding the deepening in the port of the southern extension for the cruise and dredging in the main port and the port of Heraklion it is emphasized that the environmental permit cannot be executed before the circulation study is approved after consultation.
He notes that the above-mentioned projects involve interventions that are likely to cause recoverable damage, because they are linked, like the project of creating a new port for cruise ships, to the problem of managing and disposing of the dredges that will arise, for the solution of which another is being sought method by PPA S.A. In particular, the disposal of the dredges in licensed land facilities, instead of their disposal in a marine area or their integration in cement boxes of another port project.
It is noted that the Piraeus Port Authority has already completed the traffic study which has been submitted as an appendix to the Strategic Environmental Impact Study to the Environmental Licensing Division of the Ministry of the Environment. However, in order to approve the traffic study and the environmental impact study, they must first be consulted by the relevant ministries and agencies, as well as the regional council, in order to have the final opinion. All projects will then be re-licensed from scratch. It is noted that a request to cancel the mentioned appeal of the municipalities of the region (Keratsini-Perama) has been decided to be discussed before the Plenary of the Court, after postponement, on September 22, 2023.
Which projects are excluded?
It is noted that the exception to the suspension decision of the CoE is only the upgrading and maintenance projects of the port’s infrastructure. One of them concerns the underground interconnection of the car terminal with the former ODDY site, with an initial budget of 5 million euros. This is a project that the Supreme Court considers to be aimed at improving the traffic conditions in the area by bypassing the Avenue of Democracy for the vehicles that will be moving in the port.
Also excluded are dredging and expansion projects of the sea front of the private shipyards of Perama for the restoration of operational grades as well as the construction and operation of a high medium voltage substation in the commercial port
Source: Skai
I have worked as a journalist for over 10 years, and my work has been featured on many different news websites. I am also an author, and my work has been published in several books. I specialize in opinion writing, and I often write about current events and controversial topics. I am a very well-rounded writer, and I have a lot of experience in different areas of journalism. I am a very hard worker, and I am always willing to put in the extra effort to get the job done.