The construction of the cables for the electrical interconnection Folegandros – Milos – Serifos begins

by

The project that will integrate the three islands of the Cyclades with the continental Electricity Transmission System is part of the fourth and final phase of the interconnection of the Cyclades and will be completed in 2024

ADMIE brings its construction one step closer electrical interconnection of Folegandros, Milos and Serifos with Santorini and Lavrio, after the selection of the final contractors for the project of the study, supply and installation of the underground and underwater high voltage 150 kV AC cables.

According to a statement:

  • The Hellenic Cables Group undertakes the cable section of the Lavrio-Serifos and Serifos-Milos interconnection (Section A’), with a total length of 170 km and a contract price of 195 million euros.
  • The Prysmian Group undertakes the cable section of the Milos-Folegandros and Folegandros-Santorini interconnection (Section B’), with a total length of 127 km and a contract price of 150 million euros.

The relevant contracts are expected to be signed within 2022 after the completion of the legal pre-contractual procedures.

The project that will integrate Folegandros, Milos and Serifos into the Continental Electricity Transmission System is part of the fourth and final phase of the Cyclades interconnection and will be completed in 2024. With its operation, the new interconnection will significantly upgrade the quality of electricity in 7 more directly and indirectly interconnected islands of the Cyclades (Folegandros, Milos, Serifos, Ios, Kimolos, Sifnos and Kythnos) throughout the year while it will allow the gradual withdrawal of the polluting and old technology power plants that are still operating in Milos and in Serifos.

The project, with a total budget of 345 million euros, has joined for co-financing of 103.5 million euros from the Recovery and Resilience Fund.

The president and managing director of ADMIE Manos Manousakis said: “ADMIE is getting even closer to the completion of the electrical interconnection of the Cyclades with the continental system. The cables, which start to be built immediately in the factories of the contractors, will connect the largest islands of the southwestern Cyclades with Attica, creating yet another powerful supply loop from the High Voltage System. We are confident that the contracting companies with their proven experience and know-how in demanding underwater interconnection projects will carry out this important energy project with technical excellence.”

ADMIEelectricityFolegandrosMilosnewsSkai.gr