The most mature extension is that of Line 2 to Ilion – In a preliminary stage the extension of the line to Glyfada and three new stations
The studies and tender procedures for the extensions of the Athens Metro are ongoing.
The most mature extension is hers Line 2 to Ilion, about 4 km long with 3 stations (Palatiani, Ilion and Agios Nikolaos).
In the same project, the extension and the modernization of the depot in Eleonas as well as the construction of an underground parking area.
The station “Palatian” it is located at the intersection of Thebes and Andreas Papandreou streets and has 2 entrances on either side of Thebes Street.
“Ilion” Station it is located at the intersection of Thebes and Elaion streets and has 2 entrances on either side of Thebes street and provision for connection-transfer of passengers with the homonymous Station of the future extension of Line 4 to Petroupoli.
“Agios Nikolaos” Station is located under the section of the road of the same name and part of the landscaped green space located between Paramythia, Olynthos, Zitsis and Ag. Nikolaou.
Given that the future operation of the Extension, as well as the other current needs, simultaneously make it necessary to find and build additional depot spaces to serve the trains, the extension of the Eleonas Depot to a neighboring area of ​​approximately 20 acres in the corner will proceed at the same time of Agia Anni and Pieria streets.
With the future operation of the extension, it also becomes necessary to upgrade and replace some Electromechanical Systems in a large part or even in the entirety of Lines 2 & 3 of the Metro, without which their further extension will not be possible.
For this reason, the digital data transmission system will be upgraded or replaced in all the stations of Lines 2 & 3.
Modifications to the specific systems will require new equipment and software both at the Control Center at the Constitution and locally at stations, wells, etc.
However, their connection to the current systems is envisaged to be done without any disruption to Lines 2 and 3.
In May 2023, the first stage of the competition started and has already been completed, and the second stage will soon follow with the submission of financial offers.
The estimated start of construction is 2026 and the start of operation in 2031.
For this specific Line 2, the future extension with 3 stations to Kamatero, Zefyri and Acharnes is being studied.
LINE 2 – Extension to Glyfada
In preliminary stage is the study for its extension Line 2 from the existing station Elliniko to Glyfada total tunnel length of 4.5 km and three new stations.
The first is located in Ano Glyfada, below Makedonia Square, the second at the junction of Vouliagmeni and Grigoriou Lambraki and the third and last in Agios Konstantinou Square in Glyfada.
According to the responsible actors of Hellenic Metro, the scalability of the Athens Metro is a given, within the framework of the maturity of the studies and under the condition of financing.
Future expansions
Extension design is another important part of the company’s object. In Athens, the person in charge of this level of planning is the OASA. At the present time, he is implementing the transport study of Attica, from which the planning, feasibility and sustainability of the extensions of the Metro network will be derived.
The extension of Line 2 south to Glyfada and the extension of the Metro to Kallithea have been studied by the Hellenic Metro in a preliminary stage, ensuring the connection of the SNFCC (Niarchos Foundation) with the Metro network.
The extension of Line 4 to the west, from the “Alsos Veikou” station to the municipalities of Ilio and Petroupoli, has been investigated, which will pass through the municipalities of Nea Ionia and Nea Philadelphia, with the possibility of transferring to Lines 1 and 2. Likewise, the extension of Line 4 north, from “Katehaki” station to Marousi, Pefki and Lykovrysi, with the possibility of transferring to Line 1.
Also, a branch of Line 4 from the “Evangelismos” station to PYRKAL, with networking on Lines 2 and 3, has been studied. The branch will form part of the future Line 5 to Haidari. Finally, the extension of Line 1 to the north, from the “Kifisia” station, to Nea Erythraia and the National Highway (Varymbobi junction) is being investigated.
Source: Skai
I have worked as a journalist for over 10 years, and my work has been featured on many different news websites. I am also an author, and my work has been published in several books. I specialize in opinion writing, and I often write about current events and controversial topics. I am a very well-rounded writer, and I have a lot of experience in different areas of journalism. I am a very hard worker, and I am always willing to put in the extra effort to get the job done.