At the meeting the latest data were examined, which do not show deterioration in buildings in the last 48 hours
In Voutes, the May Day was found once again at noon Mayor of Heraklion Alexis Kalirinos, Convincing a meeting with the participation of scientists of the Hellenic Authority of Geological & Mining Research (EAGME) Eleftheria Boyatzis and Yiannis Michalakis who conduct autopsies in the settlement.
At the meeting, according to cretapost.gr, which also participated by the Deputy Mayor of Civil Protection Manolis Heretis, the Secretary General of the Municipality of Maria Skrafnakis, the President of the Vouti Babis Babis Alogdianakis, the Director of DEYAI They do not show a deterioration in the cracks of buildings in the last 48 hours.
That is, the special glass cranometers were placed. At the same time, it was reported that a vulnerable subsoil of margins and possibly gypsum such as this one can even be affected by small but long -term leaks and various additional measures were discussed that can be implemented immediately and with the aim of accelerating the “dehydration” of the area in which the area is observed.
In particular it was decided:
-To cut the water supply in the “Mesochoria” of the settlement in question and to supply water to the houses inhabited by a temporary external network.
-To detect the other wells (sarnits) that may be in closed houses and if they have water to be drawn from DEYAI, according to the original appeal.
-To cover the rainwater rack in Mesochoria.
-To control cameras the interior of water supply and sewer networks to detect possible leaks.
In the next few days, expected and the first, summary of EAGME for the causes of the phenomenon and ways of radical.
In a statement shortly after the end of the work meeting, the Head of EAGME’s Technical Geology settlement Eleftheria Boyatzis said that it has not yet been clarified what caused the moves but expressed its optimism about developments. However, it finds it extremely likely that the moisture factor will contribute to the manifestation of the phenomenon.
The Mayor of Heraklion Alexis Kalirinos stressed that it is positive that in the last 48 hours of observation of cracks, through the cash network immediately placed by the Municipality of Heraklion, there is no change in the data. It is also positive that it is positive to remove the scenario of a general, primary landslide phenomenon, in accordance with the autopsies of the experts of EAGME. Alexis Kalirinos stressed that there are factors to be investigated, according to the program submitted by the Municipality of Heraklion and referred to the new measures to be implemented tomorrow (Friday 2/5), which will show their effectiveness in just a few days. In any case, as the Mayor of Heraklion pointed out, the Municipality is on hand even for the complete replacement of the networks if this is deemed necessary.
In his statement, Vouquis Babis Alogdianakis, in a statement, thanked all the services, local and central, for the immediate reaction and referred to the statements of the special sciences that conducted autopsies and stressed that there was no reason to worry about the residents of the settlement. He also said that the cameras that will control the drainage network will be clarified whether older cement pipelines are present, so as to be replaced.
The Head of the Crete Unit of EAGME Yiannis Michalakis said that the “witnesses”, the indicators placed on the craps, show that there has been stability in the last 48 hours. He also emphasized that the geological conditions on the hill of Voutus and peripherals are being controlled overall, other factors that may contribute to the problem, such as drilling, as well as the composition of the geological strata of the area, are being examined.
It is recalled that on Wednesday 30/4 it was carried out by DEYAI workshops and pumping water from cave wells (sternites) located in the house of the stairs, as recommended by the Scientific Working Group created by the Mayor of Heraklion Alexis Kalinos. In the presence of Professor Apostolos Alexopoulos, DEYAI President George Vourexakis, Director Manolis Kosmadakis, President of the DK. Voula Babi Alogdianakis and Geologist Takis Sofiou, about 20 cave wells were checked, of which only two had rainwater totaling less than three cubic feet and derived with special equipment.
It is emphasized that DEYAI has appealed to residents and those who know the existence of more despair of wells, to contact 2810529351 in order to immediately check the check.
Source: Skai
I have worked as a journalist for over 10 years, and my work has been featured on many different news websites. I am also an author, and my work has been published in several books. I specialize in opinion writing, and I often write about current events and controversial topics. I am a very well-rounded writer, and I have a lot of experience in different areas of journalism. I am a very hard worker, and I am always willing to put in the extra effort to get the job done.