Completed sanitation of polluted areas in Greek related to previous uses, such as military installations, airport, etc.

The project is the largest soil and groundwater decontamination project in Greeceaiming to rehabilitate the entire area of ​​the former airport area and minimize waste generation, in an area that is undergoing the largest urban regeneration in Europe by Lamda Development.

In particular according to information from Lamda that has been made public, more than 60,000 tons of contaminated soil corresponding to 14 Olympic-size swimming pools and 3,700 m3 of underground water they have been cleaned up.

At the same time, they are also advancing with rapid steps flood protection projects, with the anti-flood shielding of the wider Hellinikon area and the coastal zone – as has been announced – being a top priority.

His arrangement stream of Trahonon with twice the capacity of the existing one, is a pioneering project that forms part of the strong anti-flood protection of the wider Hellinikon area.

According to the company’s data, the remediation of the contaminated groundwater continues in the first half of 2024.

The new, modern city of Ellinikos, as pointed out by the company, is “shielded” against the consequences of climate change, which are already visible around us. The stream bed is released, with the aim of revitalizing the local ecosystem and creating a green recreation area. The length of the stream is 3 km and the maximum excavation depth is up to 8 meters. Excavations for the anti-flood works are 60% complete. Its completion is expected in July 2024. In addition, 88% of the excavations and 65% of the concreting of the central rainwater collectors have been completed. The stream zone is turned into a green recreation area. In full progress are the demarcation works and the stream of the Airport or Evryalis, as it was known in the past. Both streams were for decades suffocated within the narrow limits of the former airport, but also of the extensive urban development on the outskirts of Ymittos.

The roads within Hellinikon are in progress

At the same time, the construction of the roads within Elliniko has begun, with underground works in the area of ​​the shopping center that will be built on Vouliagmeni Avenue, as well as excavations on the beach front and in the area where the houses will be built. The road works will be completed in the second quarter of 2026.